Objective
Partially occupied, the site operation had to be maintained at all times. Operations were planned and liaised fully with site administration to minimise disturbance with the end users.
Solution
We completed the internal fit out works to One and Two Smithfield in Hanley, Stoke on Trent including reconfiguration of office areas and installation of bespoke glazed screens and doors to lift areas.
KEY TASKS
- Reconfiguration of office areas
- Bespoke glazed screens and doors
- On-site liaison to maintain operations
Milestones
Key stages in the Smithfield Office Regeneration
WEEK 1
Phase 1 starts at Smithfield One
Our mechanical team and project managers arrive to…
WEEK 4
Phase 2 – Glazing and Air Conditioning