Olympus Global

COMMERCIAL REFURBISHMENT

PROJECTS //

Olympus Global

COMMERCIAL REFURBISHMENT

SECTOR
VALUE
DURATION
COMMERCIAL
£200k
12 WEEKS

Objective

To meet the needs of this automotive component specialist we were asked to design and install a new mezzanine floor, offices including board rooms, test rooms, and toilet facilities.

Solution

We completed the internal office alterations and the new mezzanine floor above the existing offices in 12 weeks whilst maintaining the operational needs of the client.

KEY TASKS

  • Formation of offices including, test and board rooms
  • Mezzanine floor design and installation
  • Creation of toilet facilities